Viking Building

Manager: Luke Winter
Start: January 7, 2008
Finish: September 30, 2008
Report Date: May 15, 2008

Gantt Chart

Week 3, 2008 Week 4, 2008 Week 5, 2008 Week 6, 2008 Week 7, 2008 Week 8, 2008 Week 9, 2008 Week 10, 2008 Week 11, 2008 Week 12, 2008 Week 13, 2008 Week 14, 2008 Week 15, 2008 Week 16, 2008 Week 17, 2008 Week 18, 2008 Week 19, 2008 Week 20, 2008 Week 21, 2008 Week 22, 2008 Week 23, 2008 Week 24, 2008 Week 25, 2008 Week 26, 2008 Week 27, 2008 Week 28, 2008 Week 29, 2008 Week 30, 2008 Week 31, 2008 Week 32, 2008 Week 33, 2008 Week 34, 2008 Week 35, 2008 Week 36, 2008 Week 37, 2008 Week 38, 2008 Week 39, 2008 Week 40, 2008
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Tasks

WBS Name Start Finish Work Priority Complete Cost
1 Wall Plate Jan 7 Feb 1 23d 100%
2 Gable end Trusses Feb 3 Feb 29 24d 100%
3 Tie Beam Trusses Feb 3 Feb 29 24d 100%
4 Pegmaking Jan 7 Mar 16 60d 100%
5 shingle making Mar 2 Sep 26 180d 5%
6 Queen Posts Mar 2 Mar 14 12d 100%
7 Purlins and Ridge Mar 16 Apr 4 18d 30%
8 Oak pegs Mar 31 Apr 29 26d 0%
9 Rafters Apr 6 Jun 9 56d 0%
10 Roof Boarding Jun 10 Jun 17 7d 0%
11 Fix Shingles Jun 18 Sep 30 90d 0%

Resources

Name Short name Type Group Email Cost